Resumo
In industrial projects delivered through fragmented subcontractor supply chains, bid leveling is usually treated as an administrative price-selection step, disconnected from production planning. This paper proposes and assesses a model that repositions bid leveling as a management control mechanism for schedule. The model combines two instruments, the Extended Bid Comparison Map (EBCM) and the Procurement Tracker (PT), and replaces the fixed lookahead horizon with a variable horizon defined by each package’s lead time. Drawing on management control theory, the model shifts control from outcomes (delivery) to actions (the purchasing decision) and uses the weekly coordination meeting as an interactive control. The model is positioned against the Last Planner System, Advanced Work Packaging and the subcontractor selection literature, and six propositions specifying mechanisms and boundary conditions are developed. Four are examined through Monte Carlo simulation. Results reveal a threshold effect: for packages with lead times below roughly half the lookahead horizon, both triggering logics are equivalent; above it, the conventional logic reduces on-time-for-production delivery to below 20% when lead time equals the horizon, whereas the proposed model keeps it above 70%. Design indefinition moderates the effect, safety margins must be proportional to lead time, and the absolute benefit grows with the number of subcontracted packages. The paper integrates production planning and control research with management control theory and offers a lean model suited to small and mid-sized contractors.
Referências
AGRAWAL, A. K.; ZOU, Y.; CHEN, L.; ABDELMEGID, M. A.; GONZÁLEZ, V. A. Moving toward lean construction through automation of planning and control in last planner system: a systematic literature review. Developments in the Built Environment, v. 18, 100419, 2024. DOI: 10.1016/j.dibe.2024.100419.
ANGELIM, V. L.; MIRANDA FILHO, A. N.; BARROS NETO, J. P.; HEINECK, L. F. M.; ALVES, A. C. Medium-term planning considering the roles of the Last Planner System in production strategy and management. Ambiente Construído, Porto Alegre, v. 25, e146585, 2025.
BALLARD, H. G. The Last Planner System of production control. 2000. Thesis (PhD) – School of Civil Engineering, University of Birmingham, Birmingham, 2000.
BALLARD, G.; TOMMELEIN, I. D. 2020 current process benchmark for the Last Planner® System of project planning and control. Berkeley: Project Production Systems Laboratory, University of California, 2021.
BASARAN, Y.; ALADAG, H.; ISIK, Z. Machine learning-based dynamic model for on-site subcontractor performance management. Engineering, Construction and Architectural Management, 2025. DOI: 10.1108/ECAM-11-2024-1563.
BATAGLIN, F. S.; VIANA, D. D.; FORMOSO, C. T.; BULHÕES, I. R. Model for planning and controlling the delivery and assembly of engineer-to-order prefabricated building systems: exploring synergies between lean and BIM. Canadian Journal of Civil Engineering, v. 47, n. 2, p. 165-177, 2020. DOI: 10.1139/cjce-2018-0462.
BINGOL, B. N.; ARDITI, D.; POLAT, G. Subcontractor selection for a construction project: optimal plan. Journal of Construction Engineering and Management, v. 151, n. 12, 2025. DOI: 10.1061/JCEMD4.COENG-16409.
CHEN, Q.; ADEY, B. T.; HAAS, C. T.; HALL, D. M. Exploiting digitalization for the coordination of required changes to improve engineer-to-order materials flow management. Construction Innovation, v. 22, n. 1, p. 76-100, 2022. DOI: 10.1108/CI-03-2020-0039.
CHEN, Q.; GARCÍA DE SOTO, B.; ADEY, B. T. Supplier-contractor coordination approach to managing demand fluctuations of ready-mix concrete. Automation in Construction, v. 121, 103423, 2021. DOI: 10.1016/j.autcon.2020.103423.
CONSTRUCTION INDUSTRY INSTITUTE. Advanced work packaging: design through workface execution. Austin: The University of Texas at Austin, 2013. (Implementation Resource 272-2).
DAVIS, J. P.; EISENHARDT, K. M.; BINGHAM, C. B. Developing theory through simulation methods. Academy of Management Review, v. 32, n. 2, p. 480-499, 2007.
DEEP, S.; GAJENDRAN, T.; JEFFERIES, M.; UGGINA, V. S.; PATIL, S. Influence of subcontractors' “strategic capabilities” on “power”, “dependence” and “collaboration”: an empirical analysis in the context of procurement decisions. Engineering, Construction and Architectural Management, 2022. DOI: 10.1108/ECAM-04-2022-0346.
DUBOIS, A.; GADDE, L.-E. The construction industry as a loosely coupled system: implications for productivity and innovation. Construction Management and Economics, v. 20, n. 7, p. 621-631, 2002.
EL-KHOLY, A. M. A new technique for subcontractor selection by adopting choosing by advantages. International Journal of Construction Management, v. 22, n. 7, p. 1171-1193, 2022. DOI: 10.1080/15623599.2019.1683694.
GÖRSCH, C.; SEPPÄNEN, O.; PELTOKORPI, A.; LAVIKKA, R. Task planning and control in construction: revealing workers as early and late planners. Construction Management and Economics, v. 42, n. 5, p. 431-450, 2024. DOI: 10.1080/01446193.2023.2270080.
JAAKKOLA, E. Designing conceptual articles: four approaches. AMS Review, v. 10, n. 1-2, p. 18-26, 2020.
KOSKELA, L. Application of the new production philosophy to construction. Stanford: Center for Integrated Facility Engineering, Stanford University, 1992. (Technical Report, n. 72).
KRALJIC, P. Purchasing must become supply management. Harvard Business Review, v. 61, n. 5, p. 109-117, 1983.
LAW, A. M. Simulation modeling and analysis. 5th ed. New York: McGraw-Hill, 2015.
MALMI, T.; BROWN, D. A. Management control systems as a package: opportunities, challenges and research directions. Management Accounting Research, v. 19, n. 4, p. 287-300, 2008.
MELO, R. R. S.; MELO, R. S. S.; REY, R. O.; FIGUEREDO, S. A.; MIRANDA, C. N.; RIBEIRO, I. S. Implementação de Last Planner em empreendimento industrial com locais e atividades não repetitivas. In: SIMPÓSIO BRASILEIRO DE GESTÃO E ECONOMIA DA CONSTRUÇÃO, 13., 2023, Aracaju. Anais [...]. Porto Alegre: ANTAC, 2023. p. 1-12. DOI: 10.46421/sibragec.v13i00.2668.
MERCHANT, K. A.; VAN DER STEDE, W. A. Management control systems: performance measurement, evaluation and incentives. 4th ed. Harlow: Pearson, 2017.
O'CONNOR, J. T.; LEITE, F.; MA, J. W. Expanding advanced work packaging to include commissioning and startup for industrial projects. Construction Innovation, v. 23, n. 5, p. 939-960, 2023. DOI: 10.1108/CI-09-2021-0173.
OUCHI, W. G. A conceptual framework for the design of organizational control mechanisms. Management Science, v. 25, n. 9, p. 833-848, 1979.
SIMONS, R. Levers of control: how managers use innovative control systems to drive strategic renewal. Boston: Harvard Business School Press, 1995.
SOTO-FERRARI, M.; CHAMS-ANTURI, O. EcoMCS: a project management application through management control systems for residential construction firms in Colombia. Operations and Supply Chain Management, v. 16, p. 254-264, 2023.
TESSIER, S.; OTLEY, D. A conceptual development of Simons' levers of control framework. Management Accounting Research, v. 23, n. 3, p. 171-185, 2012.
VRIJHOEF, R.; KOSKELA, L. The four roles of supply chain management in construction. European Journal of Purchasing & Supply Management, v. 6, n. 3-4, p. 169-178, 2000.